Nightly traffic delays to come as lanes will close on QEW in Mississauga

By

Published December 2, 2024 at 1:49 pm

Lanes closed QEW in Mississauga through mid-December 2024.

Nighttime and overnight traffic will face potential delays on the QEW in Mississauga seven nights a week through the third week of December as major work continues on the highway bridge over the Credit River.

The nightly and overnight closures of four lanes on the busy section of highway through Dec. 20 are expected to cause the delays. Two eastbound and two westbound lanes between Erin Mills Parkway and Hurontario Street will be shut down to traffic at various times in the late evening and overnight hours.

Officials with the QEW/Credit River Improvement Project overseeing the major bridge rehabilitation work said in an email update the lanes will close from as early as 10 p.m. until as late as 8 a.m. the following mornings.

At some times, only one lane in each direction will be closed to traffic. However, all four lanes will be shut down for most of the late evening and overnight hours during the scheduled closures.

In addition, two highway ramps — QEW eastbound off-ramp to South Sheridan Way and South Sheridan Way on-ramp to QEW eastbound — will be fully closed to traffic from midnight this Thursday until 5 a.m. Friday morning.

Nighttime/overnight closures and other restrictions have been commonplace since 2022 both on the QEW and on nearby roads due to the massive bridge project that began nearly three years ago.

No specific completion date for the work has been provided.

Aerial view of ongoing work on the QEW in Mississauga, fall 2024. (Photo: QEW/Credit River Improvement Project)

More traffic disruptions are anticipated as work continues in the coming weeks and months. Night and weekend work along the 2.6-km stretch of the QEW from Hurontario Street to Mississauga Road, and beyond, is expected to impact traffic for the duration of the project.

For more details, visit the project website.

In a recent project update, officials noted several major components of the massive bridge rehabilitation job have been completed as work continues through the fall and into winter.

Most recently, the QEW eastbound alignment was restaged and traffic is now running on the new Mississauga Road overpass, officials said.

Additionally, back in July, paving and line painting on the QEW eastbound was done and in June, demolition and removal of the south section of the existing Credit River bridge was completed.

Moving forward on the $313.8-million project, which is being completed by EllisDon Corp. and Coco Paving Inc., ongoing activities in the coming months include:

  • work on the Mississauga Road multi-use path
  • construction and rehabilitation of the existing bridge
  • work on the Mississauga Road interchange
  • work on the pedestrian-cyclist crossings over the QEW
  • QEW median improvement work

Map shows area of the QEW being worked on as the Credit River bridge is updated. (Image: QEW/Credit River Improvement Project)

EllisDon Corp. and Coco Paving Inc. were awarded the contract in late 2020 and work began in 2021/22.

The project, first studied by Ontario’s Ministry of Transportation in 2013, initially called for demolition of the existing 840-ft.-long bridge, which was built in 1934 and expanded in 1960.   

However, public outcry and strong opposition from Mississauga city council in late 2019 changed the provincial government’s mind and it was decided the existing span, located just east of Mississauga Road, would instead be rehabilitated.  

The province said earlier that based on the feedback it received in the aftermath of the initial demolition announcement, it made the decision to preserve the original heritage structure of the bridge, which is owned by the Ontario government. 

INsauga's Editorial Standards and Policies