Four lanes will shut down nightly for the next month on QEW in Mississauga

By

Published October 31, 2023 at 11:32 am

QEW lanes in Mississauga closed nightly

Four lanes on the QEW in Mississauga will be shut down to traffic nights/overnights for the next four weeks as work continues on the highway bridge over the Credit River.

According to officials with the QEW/Credit River Improvement Project overseeing the major bridge rehabilitation work, a pair of eastbound lanes from Erin Mills Parkway to the Credit River Bridge and two westbound lanes between Hurontario Street and Erin Mills Parkway will be impacted by the closures.

The lane closures will take place through Nov. 30 at various times, including on weekends, between as early as 10 p.m. and as late as 8 a.m. the following mornings.

Additionally, the QEW eastbound off-ramp to South Sheridan Way will be fully closed to traffic from Wednesday at midnight until 5 a.m. Thursday morning.

Temporary nighttime/overnight closures and other restrictions have been commonplace since 2022 both on the QEW and nearby roads due to the massive project that began two years ago.

More traffic disruptions are anticipated as work continues in the coming months. Night and weekend work along the 2.6-km stretch of the QEW from Hurontario Street to Mississauga Road, and beyond, is expected to impact traffic for the duration of the project.

For more details, visit the project website.

INsauga's Editorial Standards and Policies